Fern Glade Road Upgrade and Pathway – Stage 2

  • Project typeUrban Road Upgrade
  • Project value$450,000
  • Contractor nameHardings Hotmix
  • Completion Date21 June 2019
Fern Glade Road Upgrade

The objective of the project is to extend the existing Shared Pathway from Wattle Avenue into Fernglade Reserve, renew the existing road seal and improve driveability and safety.

 Works will include:

  •  Continue the existing Shared Pathway from Wattle Avenue to the Emu River Bridge
  • Remove the existing seal, regrade the road and improve drivability followed by a new seal.

  • Replacing the safety barrier on the eastern side of the road and extending it.

  • Regrading and sealing the car parking area opposite Wattle Avenue and delineating the pathway across the new seal.

The Shared Pathway alignment will follow the road, protected by a new safety barrier, for a short distance, cross the existing small gully as a raised timber boardwalk (similar to Stage 1) and continue along the alignment of the existing gravel track above the road embankment through to the Emu River Bridge.

 

Contact details

Jarrod Denny – Senior Technical Officer
03 6430 5739 or 0490 891 406

Location

Fern Glade Road, Burnie 7320  View Map

Google Map